PM KPI

Allows user to review the PM plans of a particular equipment or the entire department, in table view and bar chart representation.

  1. Click on PM tab from the left menu.

  2. Make sure that the PM Plan By Year from the top menu is highlighted.

  3. User can select individual equipment tag by inputing the tag number. User can input a sub-string of the tag number instead of the full tag number, i.e. you can input 101 to locate a tag number A-101. Select the correct Plant and Department. Hit "Enter" to invoke the search. Equipment tag field can be blank to invoke search for the entire Plant and Department.

  4. All relevant matches will be displayed in the resultant table and chart. Please note that the PM KPI is displayed by financial year. KPI (Month) is calculated by dividing the Actual PM done by the Planned PM for that month. KPI (Year) is calculated by dividing the total Actual PM done by the total Planned PM for the whole year.